  • RPAX Updates (Cont)

    In the past, Tasks that were completed or cancelled would still show recommended forecast dates when updating the critical path (re-casting the project). This occurred when a task was completed or ...

  • RPAX Updates

    Tasks that are marked as Cancelled or Complete will no longer penalize the project’s RPAX score for the following items: Missing Duration Missing Work Estimate Missing Dependencies Excessive Durat...

  • Billing Code

    To accommodate those users who were needing a second pair of Cost Code structures for their payroll system, the Billing Code has been activated and is now visible in the detailed payroll file. Bil...

  • Import Bid File

    •In the “More menu” in a project, “Import Bid File” will now be available. •Once selected users will first be prompted to download and fill out an Excel Template, then to validate and upload the t...

  • Version 28.0 Release Notes-Workspace

    Within Tasks & Project PowerGrids, an additional menu option is available for “Workspaces”. Workspaces allows users to have packaged views with specific columns and sorting options saved. Users wi...