In the past, Tasks that were completed or cancelled would still show recommended forecast dates when updating the critical path (re-casting the project). This occurred when a task was completed or cancelled when a recommended forecast date was present on the task.
Unless Compress Timeline is turned on the for the project, we use the forecast dates to determine the downstream critical path recommendations.
Moving forward, completed or cancelled tasks will:
- Display the forecasted date in blue on the task in the critical path view
- Not display as a recommended change date by default, customers will have the ability to opt in those completed or cancelled tasks if they wish with a new filter option on the Critical Path update view.