To bulk accept the tasks through the notification area please see the steps below.
- Navigate to the Notifications area via the left navigation.
- Select List View from the view menu.
- Select Message Type from the Group menu.
- On the Task Assignments grouping header select the Archive All icon. This accepts and archives ALL tasks that have been assigned. This can be applied to any of the task groupings.
Please note, if you are expecting a notification for a task, but it has not yet appeared, the project status needs to be updated to In-Progress. Office suppresses task assignment notifications while the project status is Planning, On Hold, Cancelled, or Complete, so those task dates can be set and resourced before any assignment notifications go out.